I-540 Orange Route

The map above is the index map.  It shows the different map pages of proposed construction by page number.  Select the page number you want a closer look at below.
Below is a list of Subdivisions near the I-540 Proposed Construction.  You can also see the Map Number as well.  This Book consists of 5 Pages that you can scroll through, Print, and View in Full Page.
Click on the map below to make Full Screen on the top right button (square). Click on the magnifying glass symbol on the top left. Enter an address to see if it’s impacted by I-540.
Kildaire Farm Rd. & Holly Spring Rd. Interchange
Below is the proposed Public Hearing and Project Schedule.  More information can be found at the NCDOT Website at https://www.ncdot.gov/projects/complete540/
Public Hearing Schedule

The N.C. Turnpike Authority and the N.C. Department of Transportation will hold a series of public meetings in February 2018 to provide information on the project, share the preliminary design of the project and gather feedback from the public.

The three public meetings and one hearing are scheduled at the following times and locations:

Tuesday, Feb. 20, 2018
6-8 p.m.

Holly Springs High School Cafeteria
5329 Cass Holt Road
Holly Springs 27540

Wednesday, Feb. 21, 2018
6-8 p.m.

Barwell Road Community Center Gymnasium
5857 Barwell Park Drive
Raleigh 27610

Thursday, Feb. 22, 2018
Public meeting: 4-6:30 p.m.
Public Hearing: 7 p.m. 

Wake Tech Community College – Southern Wake Campus
Student Services Building L.
Rooms 212, 213, 214
9101 Fayetteville Road
Raleigh 27603

The meetings will be open-house style and citizens can stop by at any time.

The hearing will include a formal presentation, followed by an opportunity for the public to provide verbal comments. Verbal comments will be recorded at the meetings for inclusion in the public hearing record.

Written comments concerning the preliminary design plans and information presented at the public meetings and hearing can also be submitted until March 23, 2018.

Information gathered in the public meetings and hearing will be used in developing final design plans for the project. All comments carry the same weight, regardless of how they are submitted.

Project Schedule
Complete 540 Project Schedule*
Design public hearing February 2018
Record of Decision published Summer 2018
Design-build contract awarded for U.S. 401 to I-40 (R-2828) Fall/winter 2018
Two design-build contracts awarded for R-2721
(N.C. 55 Bypass to U.S. 401)
Spring/summer 2019
Design-build contract awarded for I-40 to U.S. 64/264 (I-495)
(R-2829)
FY 2027
*Subject to change.
Visit Us On FacebookVisit Us On LinkedinVisit Us On TwitterVisit Us On Google PlusCheck Our Feed